Project Summary

Total Project Budget: $143.8 Million
Referendum Funds: $130.0 Million
Contracted to Date: $62.2 Million

Waubonsie Valley High School opened in 1975, with multiple additions added in 1991, 1992 and 1995. As the building approaches its 50th anniversary, significant reinvestment in the facility is necessary to ensure the building continues to serve the community for the next 50 years.

The master facility plan for Waubonsie Valley High School identified significant needs due to aging infrastructure, poor circulation, limited visibility, a lack of natural daylight, and programmatic inequalities compared with other District 204 high schools and neighboring districts.  

Comprehensive improvements to Waubonsie began in May 2025 with the renovation of the auditorium. The next phase of work will begin in the Spring of 2026 and continue over several years. Planned improvements include:

  • Secure vestibule at the front of the building for checking in all visitors and enhancing security
  • Mechanical upgrades and system replacements throughout the building
  • A reimagined main office, atrium and commons space, improving circulation and movement throughout the building, increasing natural daylight, and modernizing the student dining experience
  • Renovations to the library and supporting spaces such as counseling, media production, and tutoring/interventions
  • Centralized class houses and department workrooms, improving student access to these services
  • Renovated classroom spaces for technology, engineering, and applied arts
  • Numerous improvements to physical education and athletics spaces, including renovated locker rooms, improved fitness, cardio and weight room spaces, and field improvements, including expanded stadium bleachers and installation of turf field
  • Building-wide LED lighting, furniture and classroom technology upgrades 

Budget Dashboard

WVHSCostSummary_p1 (PDF)
WVHSCostSummary_p2_1 (PDF)

Photo Gallery

An empty performance stage with a raised platform, lighting, and props on floor.

Waubonsie Valley - auditorium renovation

A large curved auditorium-like space featuring a raised stage and seating.

Waubonsie Valley - auditorium renovation

A large, empty indoor space with a stage and scattered construction materials.

Waubonsie Valley - auditorium renovation

A large, tiered auditorium featuring a background stage and floor markings.

Waubonsie Valley - auditorium renovation

Concrete tiered seating under construction facing a stage in an auditorium.

Waubonsie Valley - auditorium renovation

Metal conduits and dirt fill a theater under construction with an excavator in back.

Waubonsie Valley - auditorium renovation

Construction site with tools, equipment, and wooden planks on the floor.

Waubonsie Valley - auditorium renovation

Indoor construction site with wooden beams and metal supports on the floor.

Waubonsie Valley - auditorium renovation

Large performance space with a stage and equipment under a curved ceiling.

Waubonsie Valley - auditorium renovation

Black theater seats in a large auditorium with a carpeted aisle facing the stage.

Waubonsie Valley - auditorium renovation

Dark green theater seats in an auditorium with a center aisle facing a stage.

Waubonsie Valley - auditorium renovation

Rows of green theater seats facing a stage and white wall with recessed alcoves.

Waubonsie Valley - auditorium renovation

Dark green theater seats facing a stage and vertical wall panels.

Waubonsie Valley - auditorium renovation

Project Plan - Photos and Renderings

A building floor plan layout featuring a detailed schematic and level legend.
A detailed first-floor layout showing color-coded rooms with a function legend.
A detailed floor plan of a second-floor space with labeled, color-coded areas.
A third-floor layout plan of a building featuring color-coded and labeled rooms.
Set of architectural floor plans showing building circulation and layout paths.
A site plan showing buildings and roads, with a highlighted development area.
Architectural floor plan schematic with main entrances and structural columns.
A floor plan of a physical education facility showing rooms for varied uses.
A detailed floor plan of a special education facility with labeled room areas.
A bird's-eye view diagram of a dining commons with kitchens, seating, and food.
An overall building floor plan featuring color-coded sections and labeled areas.
A floor plan of a physical education facility showing various labeled spaces.
An overall floor plan of a building showing room layouts along with a legend.
An overall floor plan of a building featuring a geometric, diamond-like layout.
A long, brightly lit hallway with vaulted skylights and architectural wall details.
Detailed campus map displaying academic buildings, library, and student facilities.
A bright, open minimalist interior featuring high ceilings and a central atrium.
Interior of an educational library with bookshelves, desks, and an American flag.
A modern, minimalist interior space featuring white walls and an upper staircase.
A long, well-lit hallway featuring tiled floors, wall chairs, and equipment.
A modern open dining area featuring tables, chairs, and city views outside.
A large dining commons or cafeteria with rows of tables, chairs, and lighting.
A long, empty tiled hallway featuring recessed lighting and a wooden desk.
A spacious, modern dining commons featuring rows of seating and large windows.
A bright modern interior space featuring white walls and a background atrium.
An auditorium with rows of seating facing a large stage, screen, and lights.
An auditorium featuring green seats and a background stage under grid lights.
An indoor auditorium under construction with a large stage and equipment.

Board Action

December 2, 2024

February 24, 2025

March 24, 2025

May 5, 2025

August 4, 2025

  1. Approval of Construction Manager's Contracts

October 6, 2025

November 17, 2025

February 9, 2026